  1. NewsClimate & EnergyDeveloping

    Microsoft pulls out of Nscale's planned UK AI data center after grid connection slips to the 2030s

    Microsoft has ended its deal to anchor Nscale's planned 50 MW AI data center in Loughton, England, after the local grid operator reportedly said enough power may not be available until the early to mid-2030s; both companies say other projects are unaffected.

    Evidence: 3 sources · 3 independent reports · 3 open questions