  1. NewsClimate & EnergyDeveloping

    Microsoft pulls out of Nscale's planned UK AI data center after grid connection slips to the 2030s

    Microsoft has ended its deal to anchor Nscale's planned 50 MW AI data center in Loughton, England, after the local grid operator reportedly said enough power may not be available until the early to mid-2030s; both companies say other projects are unaffected.

    Evidence: 3 sources · 3 independent reports · 3 open questions

    Happened in AI Editors2 min read

  2. NewsClimate & Energy

    FERC rejects PJM's plan to curtail new data centers first in grid emergencies, but approves a large-load registry

    In a 9 October order, US regulators rejected PJM's proposal to let the grid operator cut power to new large loads such as data centers that do not bring their own supply, saying the choice belongs to states, while accepting a 50 MW definition and a registry.

    Evidence: 4 sources · 1 official record · 3 independent reports · 3 open questions

    Happened in AI Editors2 min read

  3. ExplainerClimate & Energy

    AI and energy: what the electricity numbers mean

    Estimates of AI's power use vary widely because they measure different things, from a single query to all data centers, so here is how to compare them.

    Evidence: 1 source · 1 official record

    Happened in AI Editors2 min read